OneNeck Data Center

Uptime Certified Tier III design of the OneNeck Mission Critical Data Center. Overall construction of 49,600 Sq. Ft. with 6,000 Sq. Ft. Raised floor Day 1 for phase 1, 6,000. Parsons’ scope included the installation of a 3MW N + 1 generator plant which is expandable to 9MW; 1800KVA UPS expandable to 5400KVA; distribution at 3.320KVA; and 2N generator controls.

Phase 2 added 6,000 Sq. Ft. of Raised Floor, UPS, PDUs, and Generation and were performed after the Data Center was fully functional.

Completing Phases 2 required a complex coordination of the electrical system to ensure reliability was maintained to the already operational facility. All upgrades were performed with no disruption to the live load of the facility.

Phase 3 will add an additional 6,000 Sq. Ft. of raised Floor and will be completed while phase 1 and phase 2 remain on line and 100% operational.